The brief
Unify the shopping-centre façade in one solution, including curved sections and the signage zone.
The solution
A cassette system laid out to the architectural intent, with a dedicated substructure for the curves.
Materials
4 mm metallic-silver composite panels, aluminum substructure, stainless fixings.
Timeline
Work was phased façade by façade so the centre stayed open - 56 days in total.